I have setup a normal backup script for monday through thursday. On Friday we do a recycle backup manually and take it off grounds (this backup not included in backup set). The mon-thur script worked fine until Wednesday rolled around again now it wants tape 3(monday) when it should want tape 1(wednesday) and my backup crashes. I have tryied to fix this with your knowladgebase but have been unsuccessfull. Please help me thanks in advance.

 

 

 

Mon-Thursday Normal backup (same 4 tapes every week)

 

 

 

Friday a full backup to take off site. (new tape every friday)

 

 

 

If this back seems unconventional or not right let me know what you suggest

Link to comment
Share on other sites

Yes its going to the "mon-thurs" backup set. This is the only backup set configured. But if I put mondays tape in and "check media" it says its good to go and it works. But I should be putting in Wednesday media.

Link to comment
Share on other sites

If you want to use a different tape every day then you need to have a backupset that corresponds with that tape every day.

 

 

 

i.e.

 

Monday = goes to Monday's Backupset

 

Tues goes to Tues backupset.

 

etc.

 

 

 

One for each day. Total of 5 if doing M-F.

 

That way when you put in Mondays...it will go to Mondays. Wed will go to Wed etc. This is the correct way in configuring your scripts.

Link to comment
Share on other sites

Heres another Question... If I want to do a Full backup (no incremental) every Friday to take off site and store away how do I do this? Create a recycle backup on Friday? Will this messup my other backup sets?

Link to comment
Share on other sites

Create a NEW MEDIA backup every Friday....that will create a new backupset on Friday that will be on a new tape.

 

If you do a recycle, it will erase everything it backed up during the week and rebackup what is there.... That is taking a chance as what if it erases the media, then attempts to backup and the power goes out? You will lose everything you backed up all week. Thus, a Recycle is not recommended on Friday's.

 

 

Link to comment