Jump to content

Script Executions are Automatically Deferred


Recommended Posts

I have a couple of scripts that are scheduled to run daily every two weeks. For some reason, the job is scheduled properly but "Defers" when it is time for it to run. It shows on the scheduled scripts properly without any indication of deferring. When I come back to the Activity Monitor at a time after which the script should have run, it shows the job did not run and is in a state of "Deferred". The only way I can run that script job is by attempting to exit from Retrospect and choosing "Executve this script now".

 

What is causing this? How does a script get deferred unless it is manually deferred intentionally? But I'm not doing that in any way.

 

Running Retrospect Professional Ver 7.5.324

Link to comment
Share on other sites

Archived

This topic is now archived and is closed to further replies.

×
×
  • Create New...